The transfer to natural gas is almost complete in Vladivostok.

18 июля 2011, 05:01
Work on gasification of CHP-2 enters its final stage.

Vladivostok. July 18. VOSTOK-MEDIA –In less than two months in the capital of Primorye, will commence supply of natural gas from the Sakhalin oil fields. Employees of the Vladivostok TPP-2 and specialists of companies-contractors have begun to test the first objects that were built under the project to transfer the station to the burning of natural gas.
Hydraulic testing started receiving tanks and storage tanks for alternative fuel number 1 and 2, are important elements of fuel oil under construction economy. In the course of the work capacity at some time will be filled with water to the projected level, which will test the strength of design and quality of welding work on the walls and bottom of reservoirs.

"