Posted 21 мая 2012,, 11:41

Published 21 мая 2012,, 11:41

Modified 17 сентября 2022,, 11:39

Updated 17 сентября 2022,, 11:39

How long do we wait for the hot water?

21 мая 2012, 11:41
Energy Vladivostok continue to test the thermal network

VLADIVOSTOK. May 21. VOSTOK MEDIA - From 21 to 25 May of Energy will conduct hydraulic tests of thermal networks Vladivostok, going from TSPVB.At the same time the strength and density of the re-test the network Frunze, Lenin, and partly Pervorechenskogo areas that receive heat from the Vladivostok TETs-1.Branch "Seaside heating networks" of JSC "Far Eastern Generating Company" on Monday, May 21 will proceed to the next stage of the thermal hydraulic test networks Vladivostok. At this time, the network of energy experience and Leninsky districts Pervorechenskogo. On the strength and density will be tested by heating from the lake to the Youth of the 1st of the river and the area Balyaeva (Mine Town), receiving coolant from the steam boiler Central (TSPVB).

"